Relocation
Problem
??????????????????????
Brief
- To
move business critical R&D server equipment to new purpose
build labs.
- Staged
decommission and re-commission to allow continuation of
normal business.
-
Racking and workstation benches to be broken down and moved
in to new labs.
-
Two separate moves over 2 weeks.
Solution
As the
client is ongoing the same dedicated project manager that has
completed all of this clients projects was assigned for the
duration of the project. The first stage was to carry out a
site survey and asset move checklist. A series of conference
calls leading up to the move date were carried out to complete
the schedule of works to minimise disruption to the business
critical R&D departments.
All
servers were then shutdown and decommissioned in accordance
with the schedule of works and packed in IT crates and moved
to storage. All racks and workstation benches were broken
down and installed in the new locations according to space
planning drawings. All servers then had to be located in
their new positions in the various racks, workstation benches
and labs.
The
client powered up the sensitive servers and tested with sign
off completed ahead of schedule.
|